Utility Projects & Landfill Closures
Merrimack Landfill Phase II Closure
Water Treatment Plant, Wolfeboro NH
General Contractor: Keymont Construction
Contract Amount: $98,950
Start Date: February
2008
Completion Date: June 2008
Birch Hill Water System, North Conway
Owner: Pittsfield Aqueduct Company
Contract Amount: $731,983
Start Date: August
2008
Completion Date: November 2008
Merrimack MSW Landfill Phase II Closure, Merrimack NH
General Contractor: CMA Engineers
Contract Amount: $1,682,400
Completion
Date: October 2004
Tuftonboro Landfill Closure, Tuftonboro NH
Owner: Town of Tuftonboro
Contract Amount: $531,548.75
Completion Date: November
2003
Barrington Landfill Closure, Barrington NH
Ownver: Town of Barrington
Contract Amount: $235,660
Completion Date:
August 2000
Route 28 Bypass Water Main, Derry NH
Owner: Town of Derry
Contract Amount: $479,462
Completion Date: July 2004
Pembroke Road Water Main, Concord NH
Owner: City of Concord
Contract Amount: $1,099,499
Completion Date: July 2004
Green Hills Water Main, Raymond NH
General Contractor: Pennichcuck Water Works
Description: Water Main & Svc Replacement
Contract
Amount: $1,308,242.31
Completion Date: May 2004
Souhegan River Interceptor Sewer Replacement Merrimack, NH
Owner: Town of Merrimack
Contract Amount: $441,450
Completion
Date: December 2006